Seventh Assurance Report from CoST Guatemala, looking at the accuracy and completeness of data on 22 projects. The seventh process uses the CoST Infrastructure Data Standard, adapted to the Guatemalan context and assesses 31 data points (or items) across core stages of a project cycle. The report highlights that low disclosure was observed in the post-contract phase (38%) with the highest levels in pre-contract phase (72%). Additionally, despite the high levels observed pre-contract, data disclosure on key pre-contract areas – budget and financing agreement – was still low.