This Assurance Report has been written following the Assurance Process conducted on the information provided by the Procuring Entity, the Ministry of Water, Irrigation, and Energy [MoWIE]. Arjo Dedessa Irrigation …
Author: CoST
CoST Ethiopia publishes three assurance reports, highlighting causes of concern in the procurement process
CoST Ethiopia has published its first assurance reports, covering three projects. The CoST assurance process interprets disclosed information to identify matters of interest or concern that could be raised with …
Assurance Report: Jimma University, laboratory and workshop building project
This assurance report is prepared for Jimma University Kitto Furdissa (Laboratory & Workshop) Building Project based on the memorandum of understanding signed between Jimma University, the Procuring Entity (PE), and …
Assurance report – Afdera Abala, road project
This assurance report is on the Hawusewa-Abala-Irebti Road contract, based on the memorandum of understanding signed between Ethiopian Roads Authority, the Procuring Entity (PE), and CoST Ethiopia. The assurance process …
Open Government is essential to delivering better value from resilient infrastructure
Written by John Hawkins, CoST Programme Manager, and Lara Samuels, CoST Communications Advisor, this article was originally published by Open Government Partnership (OGP) here. There has been much discussion in …
CoST workshop in Peru to develop infrastructure transparency in Latin America
From 22-23 October, the Comptroller General’s Office of the Republic of Peru hosted a CoST regional workshop in Lima to support Latin American countries in strengthening transparency and accountability in …