CoST Uganda

Prior to CoST: Public infrastructure in context

While Uganda has passed laws to curb corruption in recent years, a failure to implement them remains a key problem within the country. According to a Transparency International survey from 2015, 69% of citizens in Uganda feel that the government does not do enough to fight corruption and 35% of respondents were afraid of the consequences of reporting corrupt practices. Transparency International’s Corruption Perception Index also shows perceptions of corruption to have steadily worsened since 2010, and Uganda has slipped from 127th place to 149th.

In the infrastructure sector specifically, procurement audits carried out in 2014 by the Public Procurement and Disposal of Public Assets Authority (PPDA) found that contracts had been corruptly awarded to pre-determined bidders. One hundred and four cases of corruption were investigated in 2014/2015 and 45 companies were suspended from procurement and disposal procedures because of corrupt and fraudulent practices.

CoST Uganda: How it all began

The CoST membership application was made by the Uganda National Roads Authority (UNRA) in 2013, focussing on a desire to enhance transparency and accountability in the infrastructure sector by adopting CoST’s core features. UNRA made a commitment to engage stakeholders, oversight bodies and procurement entities with the CoST approach through monitoring, disclosure and knowledge sharing.

Since joining CoST in 2014, Uganda has continually worked to embrace the initiative, showing a strong commitment to its core features of disclosure, assurance, social accountability and multi-stakeholder working. CoST Uganda released its first scoping study in 2017 which was declared to be a ‘’recipe for change’’ by the Minister of Works and Transport, Monica Azuba Ntege.

The study captured a baseline measure of transparency in public infrastructure in Uganda and demonstrated how CoST can be used and adapted to add value to its delivery. It revealed that Uganda has an ‘enabling environment’ for the implementation of CoST, but that there is still work to be done. Issues such as data capacity, a lack of judicial appeal mechanisms, the attitude of public officials, limited civic engagement, and poor information storage systems provide a challenge to implementing reform.

The study recommended that the government adopt a legal mandate for data disclosure in accordance with the CoST IDS It also recommended increasing access to information for citizens, building the capacity of citizens to use the information and forging links with other open data initiatives to increase CoST’s impact.

The four features of CoST

The core features of CoST: disclosure, assurance, multi-stakeholder working and social accountability, provide a global standard for CoST implementation in enhancing infrastructure transparency and accountability.

Disclosure in Uganda

The disclosure process ensures that data about the purpose, scope, costs and execution of infrastructure projects is open and accessible to the public, and that it is disclosed in a timely manner.

After the 2017 Scoping Study revealed low levels of disclosure in procuring entities, the CoST Uganda multi-stakeholder group (MSG) embarked on disclosure training sessions with the eight agencies concerned. These training sessions led to a marked increase in disclosure: for instance, the Ministry for Education’s disclosure rate increased from 33% in 2017 to 83% in 2018.

After a concerted effort from CoST Uganda and its host, the Africa Freedom of Information Centre, the Public Procurement and Disposal of Public Assets Authority (PPDA) has redesigned the Government Procurement Portal (GPP). It now incorporates 20 data points of the CoST Infrastructure Data Standard (CoST IDS), and is working towards disclosing the full 40 data points as required by the standard. CoST Uganda’s long-term goal is to develop an infrastructure section on the GPP which will enable the public to access information on all projects disclosed using the CoST IDS. CoST Uganda is also working with PPDA to incorporate the Open Contracting for Infrastructure Data Standard (OC4IDS) into the GPP.

Assurance

We promote accountability through the CoST assurance process – an independent review of the disclosed data by assurance teams based within CoST national programmes. 

CoST Uganda has produced three assurance reports: one in 2017, one in 2018 and one in 2020.

The first assurance report analysed five contracts from three procuring entities which were: Kampala Capital City Authority, Uganda National Roads Authority and Wakiso Local Government. The report highlighted issues such as delays in procurement, limited project supervision, a lack of assurance, limited citizen involvement. Levels of disclosure were also found to be insufficient: on average disclosure was just 50% of the information required by the CoST Infrastructure Data Standard.

The second assurance showed a marked improvement in overall rates of disclosure, which increased by 29% in 2018. The report also showed that procuring entities subject to the assurance process disclosed 62% of data in line with the CoST IDS. The report looked at projects overseen by the Ministry of Education and Sports, the Ministry of Works and Transport and Wakiso District Local Government.

Multi-stakeholder working

CoST brings together stakeholder groups with different perspectives and backgrounds from across government, private sector and civil society. Through each national programme’s Multi-Stakeholder Group, these entities can guide the delivery of CoST and pursue infrastructure transparency and accountability within a neutral forum. 

The Multi-Stakeholder Group (MSG) comprises 11 members with three members from civil society, five from government and three from the private sector. The CoST champion is the Ministry of Works and Transport, and the Chairperson is Hon. Nathan Byanyima of Uganda Bus Operators Association.

Speaking about the impact of CoST, Hon. Nathan Byanyima said: “(the assurance process) aims to identify good practice and areas of concern, and to engage stakeholders. But in the longer term, it aims to ensure infrastructure projects are better planned and better delivered.”

Social accountability

The social accountability feature of CoST ensures that information on public infrastructure projects are in the public domain. CoST works with stakeholders such as the media and civil society to promote the findings of the assurance process and ensure decision makers are held to account.

One of the main ways CoST Uganda has engaged with citizens has been by holding ‘barazas’. Barazas are a Ugandan tradition in which different stakeholders come together for constructive dialogue as a way to hold decision-makers to account. These have been instrumental in improving relations between local community and government and have improved infrastructure project delivery as a result. CoST’s first baraza was held in Wakiso District in 2017 where the findings of the first assurance report were discussed.

Speaking about the impact of the baraza, Wakiso District Engineer, Samuel Mwesigwa said: “The CoST barazas have been a turning point. They opened our minds to the relevance of involving citizens in infrastructure project delivery, from planning right through to completion and post-completion phases.”

CoST Uganda also conducts training for journalists, the private sector and civil society. These efforts are complimented by surveys which compile stakeholder feedback on the work CoST Uganda carries out. A recent citizen survey included a number of suggestions, including increased citizen participation through barazas, a desire for more training sessions for public officials and higher disclosure levels. CoST has used this and other surveys to inform its activities, some of which are listed below.

Next steps

CoST Uganda’s plans for 2019 include:

  • Continuing disclosure sessions with procuring entities and conducting the third assurance report, covering 14 projects
  • Increasing the MSG’s capacity in data analysis
  • Publicity of the citizen survey findings
  • Strategic engagement meetings with key stakeholders such as the CoST Champion and Parliament
  • Continuing the programme of community barazas
  • Hosting awards for journalists involved in infrastructure project analysis.

Get in touch

CoST Uganda Country Manager
Olive Kabatwairwe
o.kabatwairwe@infrastructuretransparency.org